Project updates

22/12/2023

Our contractor, Higgins are currently in progress with remedial works, with piping being installed in Phase 1 car park.

They will move into Phase 2 once installation of piping in phase one is complete. Pipe installation in both phases is expected to be completed by mid-January.

This will be followed by Phase 2 in early February, which includes the substation, finalising all pipe works and removing the CHPs and ductwork.

Once Phase 2 substation is clear and all pipe work is installed, Higgins will then fit a power heat exchanger, pumps and connect plant in the Phase 2 substation .

These works are expected to be completed by the end of February, early March.

As works progress more updates will follow.